By Julian Campbell · CompanyWatch, GlobalBizSight
The honest answer for any company weighing a small modular reactor order today is this: do not price Unit Two off the brochure — price it off the first build's audited milestones. The decade-scale driver behind that rule is simple. AI-driven electricity demand is pulling utilities back toward firm, clean capacity, and first-of-a-kind projects now set the commercial terms for everyone who follows. That is why Ontario Power Generation's acknowledgment that its BWRX-300 at Darlington — described as North America's first small modular reactor — is late and over budget, with schedule updates withheld until mid-2027, matters far beyond one Canadian site. The gap is not a reason to abandon the technology; it is the exact checklist a disciplined buyer should write into the next contract.
Conclusion first: the program continues, but the first unit has slipped on both time and money, and the next scheduled update is a long way off.
Ontario Power Generation (OPG), the state-owned utility, has acknowledged that the GE Vernova Hitachi Nuclear Energy BWRX-300 is late and over budget, and reporting in November 2026 by Power Engineering records that the project will miss its 2030 start date and its C$7.7 billion first-unit budget. Canada's Major Projects Office lists the first SMR at $7.7 billion and the full four-unit, 1,200-megawatt plant at $20.9 billion in 2024 dollars. Demand context explains the urgency: Ontario's energy minister Stephen Lecce has tied the program to projected electricity demand growth of 75% by 2050, as FastBull reported. One caution before anyone turns these figures into unit economics: World Nuclear News notes the C$20.9 billion estimate includes financing interest and escalation costs, so it is not an overnight-construction figure and should not be compared naively with other technologies' sticker prices.
Because in this industry the second buyer underwrites the first buyer's learning curve. The framework term is first-of-a-kind (FOAK) risk: the industry's label for the cost, schedule and regulatory uncertainty concentrated in the first unit of any new design, which series production is supposed to amortize. TD Cowen analyst Marc Bianchi has described the demand-side version of the problem — customers are reluctant to sign for a first reactor because it is costlier and riskier than the units that follow, as covered by Wall Street CN. A first build that goes quiet stretches that uncertainty across the whole platform instead of letting each milestone retire it.
The stated case for SMRs remains capability, not delivery evidence. The IAEA notes that advanced technologies such as SMRs and microreactors can produce baseload and dispatchable electricity; the Department of Energy envisions advanced reactors varying from tens of megawatts to hundreds of megawatts; the IEA connects the rise of SMRs, alongside a new wave of large reactors built on time and on budget, with possibilities for power systems in Europe, the United States and Japan. Energy Monitor adds that SMRs are not forecast to reach the commercial market before 2030, and that their pitch rests on lower up-front capital costs per reactor. The Information Technology and Innovation Foundation puts the capital argument plainly: a 300-megawatt SMR facility requires far less up-front capital than a standard 1,000-megawatt plant. Every one of those statements describes possibility; none of it is delivered until a first unit proves schedule discipline.
Conclusion first: the same utility, on the same site, has already demonstrated it can publish progress and deliver — which makes the SMR's reporting gap a governance choice, not an incapacity.
While the BWRX-300 slipped, OPG was completing the C$12.8-billion refurbishment of Darlington's four existing reactors. The Globe and Mail reported in May 2025 that the refurbishment remained on schedule even as the SMR's numbers rose; by February 2026, the American Nuclear Society recorded construction complete roughly four months ahead of schedule and about C$150 million under budget. That contrast is the most useful fact in this file for later buyers. The refurbishment ran under continuous, published milestone reporting; the SMR has gone quiet until mid-2027. Same owner, same site, two different disclosure regimes — and the one with visible milestones is the one that finished early and under budget.
| Path | What it means | Best suited to | Main risk | Evidence to demand first |
|---|---|---|---|---|
| Sign now | Commit to a later unit on reference-plant terms to lock a production slot | Buyers with hard 2030s clean-capacity mandates and board tolerance for FOAK carry | Paying an uncertainty premium set in silence | Contractual milestone clauses with re-opener rights |
| Condition on milestones | Sign an option now; convert to a firm order only when design freeze, long-lead forging delivery and construction start are evidenced | Most corporate buyers; balances access and discipline | Losing queue position if milestones slip | Status bands, reason for movement, next decision point |
| Substitute or defer | Buy firm attributes from operating assets; revisit SMRs after the first unit reports | Buyers whose need date falls before 2030, since commercial SMRs are not forecast before then | Substitutes carry their own wait | Verified delivery dates and grid-queue position |
The trade-off is asymmetrical. Signing now buys queue position with money; conditioning buys information cheaply; substituting buys certainty about technology but not about timing. On that last point, Lawrence Berkeley National Laboratory data cut both ways: solar, battery storage and wind make up 95% of active capacity in US interconnection queues — roughly 2.6 terawatts by 2023 — and completion rates in that period ran from about 11% for batteries to 31% for gas projects. Substitution trades technology risk for timing risk. For most corporate buyers the conditional path dominates: it keeps the SMR option alive at the price of a deadline, and it forces the supplier ecosystem to compete on evidence.
Conclusion first: three checkable signals, published quarterly, would let outsiders tell progress from drift without exposing anything sensitive.
The format matters as much as the list: status bands rather than single confident dates, the reason for any movement, the next decision point, and redactions only where security or contract terms genuinely require them. This is the same disclosure-before-commitment logic this desk has applied elsewhere, from compute concentration ahead of a listing to a media mandate built on weak disclosure: commitments made by others should be auditable before money moves. The claim has limits, and they are real. Milestone publication fails where it would reveal security-sensitive details or force false precision on unsettled engineering — but a status band with a stated reason cures the false-precision objection at almost no cost.
No. OPG has acknowledged the unit is late and over budget, and will miss both its 2030 start date and its C$7.7 billion first-unit budget, with the next schedule update due in mid-2027. The four-unit program continues on the utility's own project page.
Not on its own. The estimate covers all four units and includes financing interest and escalation, so it cannot be read as an overnight cost per kilowatt. Lower capital cost through series production, purchasing discipline and repeatability remains a claim the second and third units have to prove.
Buyers with capacity needs before 2030 cannot wait, because Energy Monitor does not forecast commercial SMRs before then anyway; their hedge is firm supply from operating assets. Buyers planning for the 2030s can act now by writing milestone-conditioned options rather than waiting passively.
Long-lead forging delivery. Design questions can be argued; forgings are physical objects in a supplier's shop, and their movement is the hardest signal to massage into cheerful news.
Sign later-unit commitments only against milestones you can audit, because when you buy infrastructure, the audited schedule is the asset.