35x35 by 2035: Why the Grid Queue Behind the Electrification Pledge Cannot Be Measured Yet | GlobalBizSight DataStories

The short answer: COP31's 35x35 pledge can be recorded as a success without a single additional kilometre of cable being laid, because it counts electricity's share of final energy use while no accepted metric counts the queue that decides when that electricity is delivered. The target has a destination, a deadline and a signature page; it has no instrument for the bottleneck.

Delegates in Antalya put one number at the centre of COP31, and a group of countries endorsed the Presidency's pledge at the Leaders' Summit on 11 November 2026, as the World Resources Institute recorded (WRI). What the text does not carry — and what the coming decade will test — is any measure of whether the projects meant to supply that electricity can reach a grid. That omission would be tolerable if waits were short or if queue data already existed under a shared definition. Neither holds.

What does 35x35 actually commit countries to?

It commits them to a share, not to a connection. The pledge sets a single figure — electricity supplying 35% of final energy demand by 2035 — and leaves delivery to national governments and the operators who run the wires. The UNFCCC's transcript of the Presidency's announcement frames the goal as a rise "from just over 20% today to 35% by 2035" (UNFCCC).

Three starting points now circulate for the same target. Reporting on the opening session put electricity at 21% of end-use energy and cited a Rhodium Group projection of 28% by 2035 (Green Carbon World). The World Benchmarking Alliance describes the proposal as a rise from roughly 23% of final energy consumption (World Benchmarking Alliance), and Down To Earth uses the same 23% (Down To Earth). Two percentage points is small enough to be waved through and large enough to decide who can claim success.

The spread is not sloppiness. End-use energy and final energy consumption draw the system boundary in different places, and efficiency gains, fuel switching and international bunkers land differently on each side of the line. Move the convention and a country can publish a 35% share built on a redefinition plus a decade of efficiency improvement while adding very little connected capacity. Fixing the denominator is a precondition for counting signatures.

Why does two points of baseline decide whether the pledge was met?

Because the arithmetic only closes if you know where it started. Rhodium's central path reaches 28% by 2035 while the pledge asks for 35%, so seven points have to be found in a decade. That requires final demand to grow slowly, clean generation to scale, and networks to connect new load and new supply at a pace most power systems have rarely managed. The first two show up in energy statistics; the third appears in no headline indicator at all.

A share can also rise with no new wire. If efficiency trims final demand while electricity use holds steady, the percentage climbs and the grid does no additional work. Both effects are worth having; only one tests whether the pledge changed anything physical. In the most detailed public comparison of the UK's electrification record, the country scores 82% on enabling conditions and 38% on deployment (GlobalBizSight DataStories) — strong on the conditions that make electrification possible, weak on the connections that make it visible.

How long does a grid connection actually take?

Long enough to swallow a planning cycle, and reported so unevenly that the answer depends on which queue you consult. An interconnection queue is the ordered list a grid operator keeps of projects waiting for a connection decision: generation and storage on one side, large loads such as data centres on the other, each passing through study cycles, reinforcement work and often re-bidding.

The direction is not in dispute. The IEA's Electricity 2026 assessment reports grid connection queues at record levels worldwide and calls for annual grid investment to rise sharply through 2030 to keep pace with demand (IEA). Alicia Argüello, writing on LinkedIn, estimates that more than 2,500 GW of renewable generation, storage and large-load projects are waiting for connection worldwide (Alicia Argüello) — one analyst's working number, not an official census, and best read as an order of magnitude.

Duration and conversion point the same way. Berkeley Lab finds time spent in US queues up about 70% over the past decade, with only 19% of projects that requested interconnection between 2000 and 2018 reaching commercial operation by the end of 2023 (Berkeley Lab). Its latest release adds the detail that matters for a 2035 target: withdrawal rates stay "relatively high (>40%) even after signing an interconnection agreement" (Berkeley Lab, 2026).

Load-side queues move faster. ERCOT was assessing more than 233 GW of large-load requests in January 2026, up almost 300% in a year, with data centres above 70% of the total (Utility Dive). By April the operator's own briefing put it near 410 GW, roughly 87% data centres (ERCOT). One quarter separates those two figures, and whatever the definitional gap between them, the queue is a moving target that no annual metric pins down.

That is the core measurement problem. A stock says nothing about flow: how long each project waits, how many applications are abandoned, how much of the total is speculative. A project that sits six years still counts toward the 2035 share once energized, but its contribution arrives late and cannot be planned around. A share satisfied by capacity connected before the pledge existed measures nothing the pledge did. Transmission reinforcement and substation upgrades run to several years in many markets, so a queue that looks manageable now can eat the whole decade if it is not cleared early.

What do the five queue indicators actually show?

Set the available measures side by side and each answers a different question. None of them, alone, tells a government or an investor whether the 2035 share is being delivered.

IndicatorWhat it capturesWhere it misleads
Queue length, in projects and MWHow much demand for connection existsInflated by speculative applications; ERCOT's move from 233 GW to 410 GW in one quarter shows how fast the number itself travels
Withdrawal and completion rateConversion from application to energizationLate withdrawals are the costly ones; Berkeley Lab puts them above 40% even after an agreement is signed
Time from application to operationThe rate at which the queue actually clearsPublished inconsistently across operators; US queue time up about 70% in a decade
Network upgrade cost allocationWho pays for the reinforcement a connection triggersRules differ by jurisdiction, so identical projects carry different bills
Distribution and behind-the-meter capacityThe fastest-growing slice of new connectionsLargely absent from transmission queue reporting

Why does the bottleneck hit developing markets harder?

Because the queue there is often a list of projects nobody proposed. ESI Africa frames the pledge for Africa around connections, cooking and who pays (ESI Africa), and analysis at ecoltdgroup puts grid finance ahead of the share itself (ecoltdgroup). Where the network was never built to reach a region, waiting time is the wrong variable.

A diagnosis of China's distribution-grid reforms makes the point from the other direction: available capacity is now disclosed, but the mechanisms separating speculative queue positions from viable projects, the triggers that release held capacity, and the principles for sharing upgrade costs still rest on administrative coordination rather than published rules (SDG China). Different power system, same pattern — the constraint is procedural before it is physical.

What is the strongest case against a queue metric?

That 35x35 is a political instrument and should be judged as one. Its job is to move finance and keep grids visible, and the Green Grids Initiative welcomed the target on roughly those grounds (Green Grids Initiative). On this account a queue baseline over-specifies a voluntary pledge, loads reporting duties onto statistical systems that are already thin, and duplicates what the IEA and national regulators do. The 2,500 GW figure already says where the blockage sits.

A sharper version comes from the countries the pledge is meant to help. Any indicator attached to a voluntary target can later be used as a test. The second global stocktake opens at this conference and is scheduled to conclude at COP33 in 2028, with technical work starting in mid-2027 (SDG China). Negotiators have watched voluntary benchmarks turn into conditions on finance before.

The reply rests on stock versus rate. A single global figure for queued capacity, however often repeated, cannot show whether projects are moving through the gate faster than last year, how many applications are abandoned, or who pays for the reinforcement that an interconnection triggers. A review scheduled for 2028 needs a rate. A template built from disclosures operators already make can standardise reporting without new statistical obligations, and a clause stating that the baseline cannot condition finance answers the worry where it starts.

What would a usable baseline contain, and where would it fall short?

Three components carry most of the weight. Queue length gives a stock comparable across markets and years. Withdrawal rates separate speculative applications from serious ones, and they cut both ways — a large queue with heavy attrition may clear faster than its size suggests, while a stable queue may be one that has frozen new entrants out. Cost allocation decides whether a project survives the gate, because the reinforcement bill is where many developments stop.

Two gaps remain. Distributed solar, storage and demand response increasingly connect at distribution level or behind the meter, so a template built on transmission queues alone would describe a shrinking part of the system. Publication can also substitute for construction: a government can release a queue report and fund nothing, and pairing queue data with the share of queued capacity holding a signed connection agreement or a committed upgrade budget makes that substitution harder to hide.

Revision is the third limit. The 21% and 23% starting points show how fast definitions move, so the annex should publish a series with stated methodology changes rather than a single number, letting a revision read as learning rather than failure.

What should decision-makers do before the 2028 stocktake?

For the Presidency the move is procedural and cheap: attach the baseline as an annex rather than a condition, build it on existing operator disclosures and IEA compilation, cover queue length, withdrawal rates and cost allocation, publish it annually beside the pledge's progress report, and let the IEA or a designated secretariat hold the definitions. A first edition in 2027 lands before the stocktake's technical phase begins mid-year, giving the review a document and investors a way to compare markets.

For companies and capital allocators, three checks follow from the same data problem. Ask for the withdrawal-adjusted conversion rate of a queue rather than headline megawatts, because a 410 GW queue that mostly withdraws is a different asset from one where two-thirds energize. Price the upgrade-cost allocation before underwriting a site. And track distribution-level capacity and signed agreements alongside transmission totals, since that is where the fastest-growing share of connections now sits.

None of this needs a treaty, a new agency or a mandatory disclosure regime. It needs one annex, a custodian and a date — and a decision, by the people who will quote 35x35 for the next decade, that a destination is not a delivery schedule.

FAQ

What is the COP31 35x35 pledge?

A Presidency proposal to raise electricity to 35% of global final energy demand by 2035, endorsed by a group of countries at the Antalya Leaders' Summit. It is voluntary and sets a share, not a delivery mechanism.

What is an interconnection queue, in plain terms?

The ordered list a grid operator keeps of projects waiting to connect — generators, storage or large loads such as data centres — moving through studies, network reinforcement and sometimes re-bidding before a connection agreement is signed.

How long do projects wait for a grid connection?

Increasingly, years rather than months. Berkeley Lab puts the rise in US queue time at about 70% over a decade, and 2025 reporting cited consultancy estimates of eight to ten years for data centres in some markets (Financial Times).

Can 35x35 be met without new grid capacity?

On paper, yes — if efficiency lowers final energy demand while electricity use holds steady, the share rises without new connections. That is exactly why a queue metric is needed to show whether anything physical changed.

What would a baseline change for investors?

It would replace headline megawatts with conversion rates, time-to-energization and cost-allocation rules, letting capital compare markets on delivery rather than on announcements.

References

  • WRI: Countries Endorse 35x35 Electrification Pledge at COP31
  • UNFCCC: COP31 Presidency announces new targets
  • Green Carbon World: COP31 opens and nuclear debates shift
  • World Benchmarking Alliance: Powering the transition
  • Down To Earth: COP31's 35-by-35 Global Electrification Push
  • IEA: Grids — Electricity 2026
  • Alicia Argüello: COP31 — the grid challenge
  • Berkeley Lab: Grid connection backlog grows 30% in 2023
  • Berkeley Lab: Transmission queue backlog eased somewhat in 2025
  • Utility Dive: ERCOT's large load queue jumped almost 300%
  • ERCOT: Large Load Update, April 2026
  • Financial Times: Queueing not a virtue when building data centres
  • ESI Africa: 35% by 2035 — whose electrification?
  • ecoltdgroup: The 35-by-35 pledge and the grid finance gap
  • SDG China: China's reform agenda under 35x35
  • Green Grids Initiative welcomes 35x35

By Julian Campbell, GlobalBizSight. Contact: info@globalbizsight.com

Brand logo

Global Biz Sight

Global business intelligence — turning scattered data into clear, actionable decisions.

Global MarketsSector DeepDivesCompany WatchMarket EntryData StoriesGlobal SaaSManager

© 2026 GlobalBizSight.

Cookie Notice

We use cookies to improve your experience and analyze website traffic. Read our Privacy Policy to learn more.