By Marc Hale · GlobalBizSight DataStories
Short answer first: the rooftops moved faster than the paperwork. Reading customs records on module shipments out of China, energy think tank Ember sized the region's buildout at 2.3 gigawatts between 2021 and 2024, against a recorded base that accounts for only about half of it. The shortfall is not a statistical curiosity. It is a business signal — hardware supply, retail prices and buyer appetite cleared the bar long before interconnection rules caught up.
Below, GlobalBizSight DataStories reconstructs one operator's decision trail inside that gap and converts it into a checklist for anyone budgeting energy capex in an import-dependent market.
Panel exports from China — still the world's largest solar-module manufacturer — ran well ahead of the capacity statistics that Caribbean registries later published. Ember's team converted those customs flows into installed megawatts, a method that captures equipment nobody ever listed in an interconnection queue. On its published country work covering 13 Caribbean markets, the resulting figure is about 2,280 MW installed from 2021 to 2024 versus roughly 1,269 MW in recorded capacity, which is why the study concludes that households and businesses have installed roughly twice as many solar panels as official tallies can see.
Read commercially, the registers are not wrong so much as incomplete: they count the systems that asked for permission, while the market counted the systems that arrived at the port.
The buying wave tracks fuel economics rather than green preferences. The report points to Pakistan, Nigeria and Cuba, where higher fuel prices pushed both homes and firms onto rooftops; island grids simply have less buffer, because domestic fossil reserves are thin and imports dominate supply. Fossil fuels still generate more than 90 percent of the region's electricity, largely as imported oil and gas, a mix that puts retail power among the costliest anywhere on earth.
Two external reference points make the price case concrete. The World Bank puts Caribbean electricity prices at around US$0.25 per kWh on average, more than double the US average, while sector reviews from Caribbean utility bodies note retail rates above US$0.40 per kWh in some small systems. At that band, a rooftop array is competing with diesel — not with a cheap central tariff.
The real leakage is physical. The arrays buyers installed are overwhelmingly rooftop units sitting outside the central power network, so midday surplus cannot be sold back and is simply lost.
| Constraint | What the data says | Business consequence |
|---|---|---|
| Fuel exposure | Fossil generation accounts for more than 90 percent of supply, mostly imported | Operating margins swing with oil markets, not with customer demand |
| Retail price band | About US$0.25/kWh regional average, above US$0.40/kWh in some islands | Paybacks are underwritten against diesel displacement, a far easier hurdle |
| Visibility | 2.3 gigawatts installed between 2021 and 2024, recorded at only about half | Grid-planning, tax and import forecasts start from an understated baseline |
| Surplus handling | Most rooftop systems are not grid-linked | Installed capital delivers less value than its nameplate rating implies |
The clearest corporate replay in this market is Digicel's mobile estate. The trigger was a storm rather than a subsidy round. When Hurricane Beryl struck Jamaica's southern coast in July 2024, it damaged the grid supply that cell sites depend on; Digicel Jamaica chief executive Stephen Murad later framed the renewables programme as a commitment given to the government after that outage and delivered within roughly eight months, according to trade coverage of the contract (developingtelecoms.com).
The design choices are what make the case reusable. In March 2025, Digicel Jamaica contracted Caban Energy, a US solar-and-storage provider, to retrofit tower sites, including towers the operator leases from Phoenix Tower International. By September 2025 the roll-out was described as covering about half of roughly 930 Jamaican cell sites (jamaicaobserver.com); Digicel Barbados announced solar-powered mobile sites with the same partner later that year (cabanenergy.com); and trade reporting positioned Jamaica as the first of up to 25 Digicel markets across the Caribbean and Central America (capacityglobal.com).
The result line the companies publish: more than 15,000 MWh of clean energy a year from the Jamaican programme, with emissions reduced by over 38,674 tons of CO2e annually, or 580,109 tons across the life of the project.
| Phase | The move | Evidence or outcome |
|---|---|---|
| Trigger | Outage of grid feed to towers after a hurricane | Network uptime, not tariff arbitrage, became the investment case |
| Structure | Third-party developer installs and operates solar plus storage | Capex moves off the operator's critical path; the same provider closed a US$50mn financing alongside the Jamaican win |
| Scale | Site-by-site deployment across about 930 towers | Roughly half of the Jamaican estate brought into scope within the first deployment year |
| Result | Diesel backup displaced, generation located on site | 15,000+ MWh per year; 38,674+ tons CO2e avoided per year |
Four lessons transfer beyond telecom:
Clean power is the cheaper option, yet the construction surge has not converted into state-level gains, because the gatekeeping rule has the wrong shape. In several markets the incumbent utility can, in practice, refuse connection to competing sources, solar included. The reform position in the report is blunt: that yes/no decision belongs with the regulator, not the utility.
Jamaica offers a working counter-model on the pricing half of that question. Under its Net Billing programme, monopoly supplier Jamaica Public Service compensates licence holders for energy exported to the grid — the licence band runs from 1 kW to 100 kW — while the compensation rate is determined by the Office of Utilities Regulation, an independent regulator (U.S. Department of State, 2024 Investment Climate Statements). The distinction matters commercially: where the export price is regulator-declared, a rooftop investor can underwrite revenue; where it is utility-negotiated, the identical project is a relationship bet.
“Secure, affordable energy is within reach for the Caribbean,” Wilmar Suárez, senior energy analyst for Latin America at Ember, said. “Leaders who act decisively will position their countries at the forefront of this historic opportunity.”
Solar installers in the Dominican Republic appear in material credited to the Presidency of the Dominican Republic.
The strongest evidence so far is Ember's customs-based estimate: 2.3 gigawatts built between 2021 and 2024, with official capacity records showing only about half, and a 13-market country tally of 2,280 MW installed against 1,269 MW recorded. Because the method converts imports into capacity, treat the level as a range and the direction as settled.
Because the first saved dollar is self-consumption, not export. Retail tariffs in the region average around US$0.25 per kWh, so each kilowatt-hour generated on site avoids a costly imported-fuel purchase immediately; export revenue is a second, later layer that depends on regulation.
Our analysis: yes, indirectly and earlier. Falling fuel-import volumes and softer retail consumption show up in national accounts and utility finances before any registry recognises the panels, which is the window analysts should watch.
Simplifying connections for new rooftop projects and shifting the connect-or-refuse decision from utilities to independent regulators.
The commercial logic transfers to any small grid buying fuel at world prices. The sequence that worked was: survive an outage shock, contract an energy specialist rather than buy assets, prove the case in one market, then replicate across a multi-country estate.
Editorial note: this DataStories case replay is written by Marc Hale for GlobalBizSight. Corrections and data requests: info@globalbizsight.com.