Can Demand Response Replace a Transmission Line? A DataStories Case Review of Grid Cost Avoidance

Only when a named resource, at a constrained location, is metered during the hours that matter and is credited with deferring one specific transmission or distribution capital item. That is the rule the 2026 infrastructure data make urgent. EU grid capital spending, unit costs and consumer fees are rising fast, so regulators must separate verified flexibility from bookkeeping claims that simply postpone the next bill.

Why did 2026 become a grid cost-review year?

On November 6, the Agency for the Cooperation of Energy Regulators published a 2026 infrastructure monitoring report that made the consumer-cost issue hard to ignore. It said larger grid investment and higher construction costs could lift EU consumer grid fees by 50% to 100% by 2050. The reported spending trends are steep. Transmission system operators raised annual capital spending 193% between 2019 and 2025, from about 10.4 billion euros to 30.5 billion euros. Distribution system capital spending rose 51% between 2021 and 2024, from 23.5 billion euros to 35.3 billion euros.

The unevenness matters. Among 18 countries that supplied investment forecasts, 15 expected 2030 spending to exceed 2025, with an average increase of 134%. The Netherlands was expected to move its 2030 investment close to five times its 2025 level. The report also placed European power infrastructure unit costs about 50% higher from 2018 to 2024. Households have begun to see the shift. Average EU household grid fees rose 40% between 2019 and 2025, from 60 euros per megawatt hour to 84 euros, and now account for about 28% of household electricity bills. From 2023 to 2025, household grid fees rose 14%, while industrial grid fees rose 38%.

The report did not recommend blocking all projects. It suggested better use of existing grids, stronger investment planning, shorter approval processes for priority projects and clearer cost sharing across borders and user classes. For DataStories, the practical lesson is procedural: a cost review should not ban flexibility. It should work as a filter — existing assets first, verified alternatives second, new hardware third, with allocation rules that match payment to benefit.

What do congestion data show about the limits?

EU congestion data also shows why flexibility cannot serve as a general substitute for missing hardware. The report said about 40% of priority EU transmission projects experienced delays, and average implementation reached 12 years. It also estimated that a one-year delay across that portfolio could cause about 4 billion euros of net economic welfare loss. Congestion costs are rising as well. Transmission operators spent about 5.4 billion euros managing congestion in 2025, up more than 25% from 2024, while cross-border congestion revenue reached about 9.2 billion euros, roughly seven times the 2019 level. A battery in one congested valley may help that valley, but it cannot replace an absent interconnector across two countries.

Avoided capital must therefore be narrow. It may mean one bay at a substation, one circuit upgrade, one interconnector capacity step or one reinforcement deferred for a stated number of winters. A general promise of efficiency does not meet that standard. If a resource can respond only once per summer, it cannot justify a year-round transmission project that would be needed during winter peaks. If it can respond only under interruptible contracts with a long notice period, it cannot relieve a fast congestion event that would otherwise require reactive control.

Case 1: Can Guangdong’s virtual power plant floor prove capital savings?

The resource landscape complicates accounting. A Guangdong screening process lists 47 virtual power plant operators that completed review, and aggregated resources must reach at least 5 megawatts and maintain response for no less than one hour. The same report notes that a park can combine storage, adjustable load and distributed solar into one virtual plant. That can mobilize resources quickly. It does not solve pricing. A single response can look like frequency regulation, capacity or energy markets, and the answer to who pays first changes the value of the same kilowatt.

A virtual power plant industry brief lists three demand response payment sources: ancillary service cost sharing, local demand response funds and grid emergency procurement. It says settlement timing differs across those channels, and post-event negotiation is the least predictable form. It also notes that ancillary service cost sharing can be allocated to commercial and industrial users according to electricity consumption. If flexibility is used to reduce a grid project, the payment mechanism must be decided before the response is counted in the review.

Case 2: Why China keeps storage out of the regulated grid tariff

The institutional setting makes the narrow test more important than it may first appear. In China, transmission and distribution pricing cost is a regulated input, and the 2019 cost audit rule excluded energy storage related costs from that category. A draft published on September 8 continued to exclude pumped hydro, new storage stations and grid-owned plant costs from transmission and distribution pricing cost, while leaving the future treatment of new storage compensation in system operation costs unresolved. An Eastmoney report framed the revision around how to allocate rising system operation costs caused by renewable variability and demand peaks, not around how to put storage into the regulated grid tariff.

These sources show that the current rule is deliberate: flexibility may be valuable, but its cost is not automatically recoverable from all grid users. Storage and demand response should enter approval review as alternatives to be measured against a specific avoided capital expenditure. They should not become regulated assets whose costs flow automatically into transmission and distribution prices. The concern behind the exclusion is reasonable. If every battery, virtual plant and response event can be charged to all users, the connection between payment and benefit weakens. The cost review should protect customers from paying twice: once for hardware that could be delayed, and again for flexibility that may never appear.

Case 3: Does a 1-gigawatt data center response reduce a line?

A large load case makes the boundary sharper. A Beijixing Transmission Network report describes a facility plan with a 1-gigawatt demand response commitment, roughly equivalent to about 700,000 households and close to one third of the facility’s maximum load. The report also states that Georgia Power considers such a commitment useful for reducing future generation investment and spreading fixed network costs over a larger volume of sales. Those claims are plausible at the generation planning level, but they do not automatically convert into transmission capital avoidance.

A facility that smooths its annual load can improve asset utilization. A response in the wrong node, or in an hour when the line is already underloaded, may avoid little capital expenditure. The bridge from flexibility to a cost review is often physical. GlobalBizSight has examined why U.S. AI data centers are bolting batteries onto gas plants, a reminder that a curtailment promise needs storage, controls, contracts and a location where the wire is actually tight.

What do new U.S. studies add to the audit test?

Recent U.S. work strengthens the case-review method rather than diluting it. Duke University’s Nicholas Institute report Data Centers and Generation Capacity over the Next Decade estimates that data center flexibility scenarios could avoid about $40 billion to $150 billion in U.S. generation-capacity needs over the next decade, mainly by reducing new gas capacity and shifting investment toward renewables. The number is system-level. It becomes a project-level rate case only when the flexible hours, location and counterfactual asset are visible.

The New York Department of Public Service’s grid flexibility study, prepared with Brattle Group, is more precise on that point. It found New York’s cost-effective grid flexibility potential could reach 8.5 gigawatts by 2040, about 21% of forecasted NYISO winter peak demand, and could avoid nearly $2.9 billion a year in power-system costs. The study modeled hourly performance, which is exactly the layer absent from a generic “flexibility saves money” claim. For a transmission audit, the relevant question is not whether New York has 8.5 gigawatts of potential flexibility, but which megawatts, at which constrained circuits, during which winter peaks, defer which named reinforcement.

CaseMeasured valueAudit question left open
Guangdong VPP screening47 operators passed review; resources ≥5 MW and response ≥1 hourDo the megawatts align with the constrained feeder, substation or interconnector under audit?
Georgia large-load plan1 GW DR commitment; about 700,000 households; close to one third of maximum loadWhich named transmission or distribution capital item is actually avoided?
Duke flexibility scenarios$40 billion to $150 billion avoided U.S. generation-capacity value over the next decadeWhich hours, regions and projects convert system savings into rate recovery?
New York flexibility study8.5 GW cost-effective potential by 2040; nearly $2.9 billion avoided annual system costIs a local reinforcement deferred, or is the saving only a portfolio average?

What is the strongest counterargument — and how to neutralize it?

The strongest counterargument is that a review rule can become a delay excuse. A grid operator may claim a response program is coming, or batteries are being built, and use that claim to postpone a project that should be approved today. If the need remains tomorrow, customers pay for congestion, reliability risk and the same line at a higher cost. The EU congestion numbers make that concern concrete. The report said about 60% of available congestion revenue was kept for future use, with a cumulative total of about 12.5 billion euros, instead of being used promptly to relieve cross-border congestion or reduce network fees. It also cited a warning that if expansion continues at the current pace, annual congestion management costs in Europe could exceed 100 billion euros by 2040, about 20 times the current level.

If a regulator accepts flexibility without measurement, a sponsor can choose the cheaper path on paper and the more expensive path in reality. A plan can advertise demand response during planning, then return to build the line after a dry summer, a cold snap or a factory shutdown ends. The review can break that loop by treating the deferral as temporary and reversible. The resource earns only for the period and location it proves it can serve. When that period ends, the asset returns to the normal queue.

Demand response compensation needs a source. If it comes from ancillary service cost sharing, the cost may land on commercial and industrial users by consumption. If it comes from a local fiscal fund, it becomes a public expense. If it comes from emergency grid spending, settlement can be opaque after the fact. A broad flexibility review without a payment cap can shift part of the bill to users who never benefit from the avoided project. The idea that flexibility belongs in cost rationality review cannot become a blanket argument for spreading flexibility costs across all users.

The response to the delay objection is a narrow test with fixed consequences. Reviewers should ask whether a named resource, at a specified location, during a limited number of hours, avoids a defined piece of capital expenditure. A regulator needs the line or substation that would be approved without flexibility, its expected cost curve, its commissioning date and the congestion or overload hours that make it necessary. If the answer is uncertain, the physical project should proceed. If it is verified, the project should be deferred for a fixed period, and the avoided cost should be audited afterward. The flexibility credit then needs independent metering at the relevant feeder, substation or interconnector. Response duration, notice lead time, reliability and rebound behavior should be verified by a party that does not own the project.

The Guangdong threshold of 5 megawatts and one hour is a reasonable floor for physical capability, but it is not proof that those megawatts relieve the bottleneck under audit. Compensation should also be capped and time limited. A battery or demand response program may earn payment for avoided capital or congestion relief, but it should not automatically earn a regulated return like a transmission asset. A sunset period is needed. If load growth exceeds the forecast or the resource fails to respond, the sponsor can return with a new counterfactual. That keeps temporary industrial shutdowns and mild weather from locking in a deferral.

Funding source should match beneficiary. If congestion revenue is available, it could be tested for targeted flexibility use, but the retained congestion revenue finding shows regulators cannot assume that money is already flowing to relief. If commercial users benefit from a substation deferral, they should see a rate element tied to that deferral. If all users benefit from a reliability upgrade, payment may be broader, but the basis should appear in the same approval. A Zhihu commentary argued that generation-side time-of-use prices could be combined with transmission distance and asset utilization to form sharper demand-side price signals. That proposal is not an implemented rule, but it points to the missing condition: prices need to show where a kilowatt hour is scarcest.

Where large loads are already changing grid plans, contract discipline has become part of the audit. Southern Co. has described 15-year minimum contracts for data centers, minimum bill provisions similar to take-or-pay structures, termination payments tied to incremental cost to serve, and collateral-backed obligations in bilateral large-load contracts. That is not a reason to assume every data center is flexible; it is evidence that regulators and utilities are learning to price uncertainty before public capital is committed.

What does a reusable audit checklist look like?

  • Start from the counterfactual asset. Name the line, transformer, bay, circuit, interconnector or reinforcement that would otherwise be approved.
  • Convert potential into project evidence. A gigawatt portfolio, such as a 1-gigawatt demand response commitment or 8.5-gigawatt state flexibility pool, is not the same thing as one avoided capital item at one constraint.
  • Meter at the bottleneck, not at the meter. Use independent metering at the feeder, substation or interconnector and verify duration, notice lead time, reliability and rebound behavior.
  • Cap and sunset the payment. Flexibility may earn payment for avoided capital or congestion relief, but it should not automatically earn a regulated transmission return.
  • Match funding to beneficiaries. Ancillary cost sharing, local funds, emergency procurement and retained congestion revenue are different money. The public file should say which account pays and why.
  • Reopen the queue if reality changes. If load growth exceeds the forecast, the resource fails to respond, or the deferral expires, the sponsor should return with a new counterfactual.

Common misconceptions

  • “Flexibility always lowers bills.” It lowers bills only when it avoids a specific asset or reduces congestion in the hours and places where the grid is constrained. Otherwise it may move costs without removing them.
  • “A megawatt is a megawatt.” A megawatt with long notice, poor reliability or rebound risk is not a transmission substitute. The timing and location determine whether the next capital bill disappears or merely waits.
  • “System-level savings automatically justify rate recovery.” Duke’s $40 billion to $150 billion estimate and New York’s 8.5-gigawatt flexibility potential are useful planning signals, but they do not prove that one named project can be deferred without further audit.
  • “Aggregated resources are simple to price.” A park combining storage, adjustable load and distributed solar can look like frequency regulation, capacity or energy markets. The first market that pays changes the value of the same kilowatt.

FAQ: What readers should ask next

Does a 1-gigawatt demand response commitment save grid customers money?

It can, but not automatically. In the Beijixing Transmission Network case, the 1-gigawatt commitment is equivalent to about 700,000 households and close to one third of the facility’s maximum load. Georgia Power sees value in reducing future generation investment and spreading fixed network costs over larger sales. Customers save money only if that response is located in a congested network and avoids a named transmission or distribution asset.

Is the Guangdong 5-megawatt, one-hour standard enough for cost review?

No. It is a credible physical floor, because 47 virtual power plant operators completed review with resources at least 5 megawatts and response no less than one hour. It does not prove the resource appears at the constrained node during the congested hours used in a capital audit.

Can congestion revenue pay for flexibility?

Only if the payment is targeted and audited. The ACER report said about 60% of available congestion revenue was retained for future use, with a cumulative total of about 12.5 billion euros. That makes congestion revenue a possible funding source, but not a self-evident one, because the money may not already be flowing to relief.

What happens if flexibility fails after a project is deferred?

The deferral should be temporary, measurable and reversible. If the resource does not respond or load growth exceeds the forecast, the project returns to the normal queue with a new counterfactual, and the flexibility payment stops or is reduced. That avoids a second bill: one for delayed hardware, and another for flexibility that never appeared.

References

  • ACER, Energy infrastructure development in Europe, 2026 monitoring report
  • Duke Nicholas Institute, Data Centers and Generation Capacity over the Next Decade
  • Duke Nicholas Institute, Key takeaways on data center flexibility
  • Brattle Group / New York Department of Public Service, New York’s Grid Flexibility Potential, Volume I
  • Utility Dive, Southern Co. contracted large load and cost-recovery tools
  • China transmission and distribution pricing draft coverage
  • Chinese regulatory cost reporting
  • Eastmoney reporting on system operation cost allocation
  • Guangdong virtual power plant screening reporting
  • Demand response payment-source brief
  • Beijixing Transmission Network large-load reporting
  • Zhihu price-signal commentary

Related reading

  • DataStories Case File: What China's 360 Terawatt-Hour Curtailment Teaches Investors About Grid Risk
Brand logo

Global Biz Sight

Global business intelligence — turning scattered data into clear, actionable decisions.

Global MarketsSector DeepDivesCompany WatchMarket EntryData StoriesGlobal SaaSManager

© 2026 GlobalBizSight.

Cookie Notice

We use cookies to improve your experience and analyze website traffic. Read our Privacy Policy to learn more.